SAFE WORK METHOD STATEMENT · SWMS-NSW-SAMPLE01

Electrical High-Risk Construction Work SWMS

Jurisdiction: SafeWork NSW · Work Health and Safety Act 2011 (NSW) · Work Health and Safety Regulation 2025 (NSW) s 291 (18 HRCW categories)

STATE: NSW (18 HRCW Schedule)
ISSUED / GIVEN TO PC: 26/11/2026
REVIEW BY: 26/12/2026
PCBU / Subcontractor
Ironbark Electrical Contracting Sample Pty Ltd
ABN: 51 824 753 556
Contact/Addr: Unit 4, 18 Forge St, Silverwater NSW 2128
Principal Contractor
Harbourline Commercial Builders (Sample Specimen)
Supervisor: Jordan Vance (Sample Leading Hand)
Workplace / Site Gate Address
142 Macquarie Street, Parramatta NSW 2150
Duty ref: WHS Regulation 2025 (NSW) ss 299 to 303
Statutory Compliance & Retention Rules (NSW):
  • Enforces the 18 High-Risk Construction Work triggers under NSW Work Health and Safety Regulation 2025 s 291.
  • PCBU must provide the site-specific SWMS to the Principal Contractor before commencing HRCW on site (s 301).
  • Worker consultation under ss 47 to 49 of the WHS Act 2011 (NSW) must be recorded on the Worker Sign-On Sheet prior to work starting.
  • Retention: Keep copy readily accessible at the workplace until HRCW finishes; retain for 2 years if a notifiable incident occurs (s 303).

2. Triggered High-Risk Construction Work Categories (3 of 18)

Work Health and Safety Regulation 2025 (NSW) s 291 (18 HRCW categories)
  • s 291(a) · TRIGGERED
    Risk of person falling > 2m

    Work that involves a risk of a person falling more than 2 metres.

  • s 291(k) · TRIGGERED
    Energised electrical installations

    Work that is carried out on or near energised electrical installations or services.

  • s 291(o) · TRIGGERED
    Movement of powered mobile plant

    Work that is carried out in an area at a workplace in which there is any movement of powered mobile plant.

3. Pre-Control & Residual WHS 5x5 Risk Matrix

Likelihood L (1 to 5) × Consequence C (1 to 5) = Score (1 to 25)
EXTREME (15 to 25)

STOP WORK IMMEDIATELY: Do not proceed until eliminated or engineered down.

HIGH (9 to 14)

Senior PCBU & Principal Contractor sign-off + higher-order physical controls mandatory.

MEDIUM (4 to 8)

Documented SWMS controls, supervision, and pre-start verification required.

LOW (1 to 3)

Acceptable residual risk: maintain controls and monitor site changes.

4. Task-by-Task Hazards & 6-Tier Hierarchy of Controls

SHOWING ALL 6 STEPS

Suggested Baseline Controls (Awaiting Supervisor Site Verification): Review each suggested control below against physical workplace circumstances (WHS Regulation 2025 (NSW) ss 299 to 303) and record any site-specific adjustments before worker sign-on.

Job Step & Activity Site Hazards Pre-Control Risk Hierarchy of Controls (Elimination → PPE) Residual Risk & Person Responsible
STEP 01
Site Gate Arrival, Principal Contractor Induction & Pre-Start Inspection (Harbourline Commercial Builders (Sample Specimen))
  • Uninducted personnel entering active construction zones or clashing with concurrent trades
  • Unidentified underground/overhead services or altered site traffic routes at shift start
L3xC4=12 (HIGH)
1. Elimination:
Prohibit entry into active work zones until Principal Contractor gate induction and SWMS sign-off are complete.
2. Substitution:
Stage material deliveries in designated off-road unloading bay rather than live site accessway.
3. Isolation:
Establish physical bunting/barricades with High-Risk Work signage around work zone prior to tool setup.
4. Engineering:
Verify residual current device (RCD) protected construction supply boards and tested/tagged leads (AS/NZS 3012).
5. Admin:
Conduct pre-start toolbox talk prior to work starting; verify White Cards, trade licences, site muster point, and worker signatures on this SWMS.
6. PPE:
AS/NZS 1801 hard hat, high-visibility day/night clothing, AS 2210.3 steel-cap footwear, and AS/NZS 1337.1 eye protection.
L1xC3=3 (LOW)
Role: PCBU / Subcontractor Site Supervisor & All Crew
STEP 02
Electrical Isolation, Lock-Out Tag-Out (LOTO), Prove De-Energised & Circuit Work (NSW WHS s 291(k))
  • Electric shock, electrocution, or arc-flash burn from live conductors, back-fed solar inverters, or adjacent circuits
  • Inadvertent re-energisation of circuits by other site trades during rough-in or fit-off
L4xC5=20 (EXTREME)
1. Elimination:
De-energise all circuits and PV DC strings completely prior to commencing work; zero live electrical work permitted.
2. Substitution:
Use battery-operated cordless insulated hand tools (18V/36V) instead of 240V mains extension leads.
3. Isolation:
Apply personal Lock-Out padlock and Danger Tag at main/distribution switchboard; lock off PV DC & AC isolators.
4. Engineering:
Test-Before-You-Touch: prove tester on known live source, test target conductors (active-neutral, active-earth), re-prove tester.
5. Admin:
Comply strictly with AS/NZS 4836:2023; post insulated LV Rescue Kit and CPR-trained spotter at open switchboards.
6. PPE:
1000V insulated electricians gloves, flame-resistant cotton long sleeves, dielectric boots, and arc-rated face shield during testing.
L1xC3=3 (LOW)
Role: Licensed Electrician / SAA Installer
STEP 03
Working at Heights (> 2 Metres): Edge Protection, Scaffold Access & Brittle Surfaces (NSW WHS s 291(a))
  • Person falling > 2 metres from roof edge, unprotected penetration, incomplete scaffold bay, or brittle polycarbonate sheet
  • Dropped tools or materials striking workers below active overhead work zone
L4xC5=20 (EXTREME)
1. Elimination:
Pre-assemble frames, brackets, and sub-assemblies at ground level to minimise duration spent at height.
2. Substitution:
Use ScaffTag-certified modular scaffold or EWP platform instead of portable ladders for work tasks.
3. Isolation:
Install continuous AS/NZS 4994 perimeter guardrails (top rail, mid-rail, toeboard) and hard covers over penetrations/skylights; barricade drop zone below.
4. Engineering:
Fit tool lanyards and scaffold brick-guards; secure ladder stiles 1m above landing only for access/egress.
5. Admin:
Inspect fall-restraint gear before shift; enforce written retrieval rescue plan and suspend roof work in high winds (> 40 km/h) or wet steel.
6. PPE:
AS/NZS 1891 full-body harness in travel-restraint mode (where edge protection is being installed), chin-strap helmet, non-slip footwear.
L1xC3=3 (LOW)
Role: Site Supervisor & Ticketed Height Crew
STEP 04
Powered Mobile Plant, Crane Lifting & EWP Movement Separation (NSW WHS s 291(o))
  • Crush or strike injury from reversing excavators, telehandlers, EWPs, or slewing mobile cranes
  • Dropped load or crane outrigger ground bearing failure near trenches or suspended slabs
L4xC5=20 (EXTREME)
1. Elimination:
Schedule crane lifts and bulk mobile plant movements outside peak pedestrian trade access windows.
2. Substitution:
Use taglines from outside the fall shadow rather than manual hand-guiding under suspended loads.
3. Isolation:
Erect physical water-filled/mesh pedestrian barriers separating walkways from mobile plant operating & crane slewing zones.
4. Engineering:
Verify daily plant pre-start logbook, reversing squawker/camera, flashing beacon, outrigger bog mats, and rated lifting chains.
5. Admin:
s 291(o): enforce positive plant-pedestrian separation, crane lift plan compliance, and dedicated spotter. Maintain positive UHF radio / eye-contact stop signals with operators.
6. PPE:
High-visibility garments to AS/NZS 4602.1, hard hat, steel-cap boots, and riggers gloves.
L1xC3=3 (LOW)
Role: Plant Operator, Dogman & Site Supervisor
STEP 05
Crystalline Silica Substance (CSS) Drilling, Chasing & Cutting Controls (NSW WHS Reg 2025 Chapter 8A)
  • Inhalation of respirable crystalline silica (RCS) exceeding the 0.05 mg/m3 8-hour TWA workplace exposure standard when drilling, chasing, grinding, or cutting concrete, brick, roof tile, or fibre-cement
  • Uncontrolled dust release or unlawful processing of engineered stone benchtops, panels, or slabs
L3xC4=12 (HIGH)
1. Elimination:
Order pre-cut fibre-cement/masonry elements off-site and cast-in ferrules before pour. Strictly prohibit manufacture, supply, or installation of new engineered stone benchtops/panels/slabs (legacy engineered stone repair/removal requires prior regulator notification).
2. Substitution:
Use score-and-snap fibre-cement shears instead of rotary power saws wherever material thickness permits.
3. Isolation:
Barricade cutting zone away from adjacent trades; strictly prohibit dry-sweeping or compressed-air blowdown.
4. Engineering:
Combine continuous water-delivery suppression OR on-tool shroud connected directly to an M-Class or H-Class vacuum extractor.
5. Admin:
Where high-risk crystalline silica processing applies, maintain a task-specific Silica Risk Control Plan (reg 529CC / VIC Part 4.5) recording crystalline silica content and exposure assessment alongside this SWMS; verify worker silica training and wet-wipe/HEPA-vacuum slurry.
6. PPE:
Clean-shaven fit-tested P2 respirator (AS/NZS 1716), wrap-around eye protection, Class 5 hearing protection, anti-vibration gloves.
L1xC2=2 (LOW)
Role: PCBU / Subcontractor Site Supervisor & Tool Operators
STEP 06
Testing, Commissioning, Housekeeping, Waste Removal & Safe Demobilisation
  • Residual stored energy during commissioning or unguarded penetrations left behind for following trades
  • Manual handling sprains/strains and slip/trip hazards from offcuts, packaging, or trailing leads
L3xC3=9 (HIGH)
1. Elimination:
Remove all redundant temporary leads, offcuts, and waste progressively so walkways remain clear.
2. Substitution:
Supply materials in <= 15kg split packs and use pallet jacks/trolleys instead of solo manual lifting.
3. Isolation:
Reinstate all permanent switchboard covers, pit lids, and perimeter guardrails before removing danger tags/barricades.
4. Engineering:
Use mechanical trolleys and team-lift aids for heavy switchboards, inverters, pipe lengths, or tools.
5. Admin:
Complete commissioning checklist and hand signed SWMS / compliance certificate copy to Principal Contractor site office.
6. PPE:
Cut-resistant gloves (Level C/D) during scrap cleanup, eye protection, hi-vis clothing, and steel-cap footwear.
L1xC2=2 (LOW)
Role: PCBU / Subcontractor Site Supervisor

5. Mandatory Licences, High-Risk Work Classes & Australian Standards

  • Unrestricted State Electrical Contractor & Electrician Licence
  • General Construction Induction Card (White Card)
  • AS/NZS 4836:2023 Safe working on or near low-voltage and extra-low-voltage electrical installations
  • AS/NZS 3000:2018 Wiring Rules & AS/NZS 3012:2019 Construction and demolition sites electrical installations
  • CPR & Low Voltage Switchboard Rescue Kit currency (refreshed within 12 months)

6. Worker Consultation & Gate Sign-On Sheet

ALL WORKERS MUST READ & SIGN PRIOR TO HRCW START

By signing below, each worker confirms they hold a current General Construction Induction Card (White Card) and required trade/HRWL licences, were consulted in reviewing site-specific hazards, and agree to follow the Hierarchy of Controls in this SWMS.

# Worker Full Name Trade / Role White Card / HRWL Licence No. Date (DD/MM/YYYY) Worker Signature
01 Jordan Vance (Sample Leading Hand) Electrical Supervisor 26/11/2026
02
03
04
05
06

7. Implementation, On-Site Monitoring, Stop-Work & Review Protocol

WHS Regulation 2025 (NSW) ss 299 to 303 (reg 299(2)(d), reg 299(3)(a)(ii), reg 300 & reg 302)
MANDATORY STOP-WORK (WHS Regulation 2025 (NSW) s 300): If work cannot be carried out strictly in accordance with this SWMS or an unanticipated hazard arises, stop the High-Risk Construction Work immediately, make the area safe, notify Harbourline Commercial Builders (Sample Specimen), and do not resume until revised controls are documented and signed off.

Baseline trade controls prepared for 142 Macquarie Street, Parramatta NSW 2150; nominated supervisor sights and aligns with site-specific rules and emergency procedures in the WHS Regulation 2025 (NSW) s 299(3)(a)(ii) Principal Contractor WHS Management Plan at gate induction prior to work starting.

  • Provide this site-specific SWMS to Harbourline Commercial Builders (Sample Specimen) for gate review and acceptance prior to commencing any High-Risk Construction Work.
  • Brief all workers at the pre-start toolbox talk in plain language, inspect physical site hazards at the work face, and record each worker’s White Card / HRWL number and signature in Section 6.
  • Verify all physical isolation locks, edge protection, shoring, plant pre-starts, and rescue equipment are installed before tools are energised.
  • Nominated PCBU / Subcontractor Site Supervisor conducts visual spot-checks at shift start, after breaks, and whenever concurrent trades enter adjacent zones.
  • Coordinate daily exclusion zones, crane/plant movements, and permit-to-work handovers with the Principal Contractor Site Supervisor.
  • Review and revise this SWMS immediately (WHS Regulation 2025 (NSW) ss 38 & 302) whenever: (a) a control measure does not control the risk as intended; (b) a notifiable incident or near-miss occurs; (c) site conditions, plant, trade scope, or work systems change; or (d) a Health and Safety Representative (HSR) or Principal Contractor requests a review.

8. Emergency Response & Principal Contractor Gate Sign-Off

Emergency & Rescue Protocol

Emergency Response: In a life-threatening emergency call Triple Zero (000) Emergency Services immediately and notify the Principal Contractor Site Supervisor via site UHF channel or gate office.

Muster Point: Awaiting site confirmation at 142 Macquarie Street, Parramatta NSW 2150: record Principal Contractor Emergency Muster Point ________________________ and Induction Time ____:____ prior to work start.

Trade Rescue Gear: Insulated LV Rescue Kit staged at active switchboard plus spotter holding current CPR & LV Rescue competency.

Medical Centre: Record Principal Contractor nominated hospital / medical centre displayed on site gate noticeboard prior to work start.

PCBU / Subcontractor Authorised Supervisor Sign-Off

Before signing below and commencing High-Risk Construction Work, I confirm I have inspected physical workplace conditions, consulted the workers carrying out the work, verified or adapted the suggested controls in Section 4 to match actual site circumstances, and recorded the site muster point and induction time.

Name: Jordan Vance (Sample Leading Hand) · Signed: __________________ · Date: 26/11/2026
Principal Contractor Gate Acceptance (Harbourline Commercial Builders (Sample Specimen))

Principal Contractor representative acknowledges receipt and review of this site-specific SWMS prior to High-Risk Construction Work commencing on site.

Site Supervisor: __________________ · Signed: __________________ · Date: 26/11/2026

SiteSWMS.com.au is self-serve commercial document software published in Sydney by Malloy Co Pty Ltd (ABN 61 704 474 055) that prepares editable Safe Work Method Statements aligned to published Australian WHS and Victorian OHS regulations; before High-Risk Construction Work starts, the PCBU/employer and nominated site supervisor inspect physical site conditions, consult workers, and confirm site-specific controls.