Electrical High-Risk Construction Work SWMS
Jurisdiction: SafeWork NSW · Work Health and Safety Act 2011 (NSW) · Work Health and Safety Regulation 2025 (NSW) s 291 (18 HRCW categories)
- Enforces the 18 High-Risk Construction Work triggers under NSW Work Health and Safety Regulation 2025 s 291.
- PCBU must provide the site-specific SWMS to the Principal Contractor before commencing HRCW on site (s 301).
- Worker consultation under ss 47 to 49 of the WHS Act 2011 (NSW) must be recorded on the Worker Sign-On Sheet prior to work starting.
- Retention: Keep copy readily accessible at the workplace until HRCW finishes; retain for 2 years if a notifiable incident occurs (s 303).
2. Triggered High-Risk Construction Work Categories (3 of 18)
Work Health and Safety Regulation 2025 (NSW) s 291 (18 HRCW categories)-
s 291(a) · TRIGGEREDRisk of person falling > 2m
Work that involves a risk of a person falling more than 2 metres.
-
s 291(k) · TRIGGEREDEnergised electrical installations
Work that is carried out on or near energised electrical installations or services.
-
s 291(o) · TRIGGEREDMovement of powered mobile plant
Work that is carried out in an area at a workplace in which there is any movement of powered mobile plant.
3. Pre-Control & Residual WHS 5x5 Risk Matrix
Likelihood L (1 to 5) × Consequence C (1 to 5) = Score (1 to 25)STOP WORK IMMEDIATELY: Do not proceed until eliminated or engineered down.
Senior PCBU & Principal Contractor sign-off + higher-order physical controls mandatory.
Documented SWMS controls, supervision, and pre-start verification required.
Acceptable residual risk: maintain controls and monitor site changes.
4. Task-by-Task Hazards & 6-Tier Hierarchy of Controls
SHOWING ALL 6 STEPSSuggested Baseline Controls (Awaiting Supervisor Site Verification): Review each suggested control below against physical workplace circumstances (WHS Regulation 2025 (NSW) ss 299 to 303) and record any site-specific adjustments before worker sign-on.
| Job Step & Activity | Site Hazards | Pre-Control Risk | Hierarchy of Controls (Elimination → PPE) | Residual Risk & Person Responsible |
|---|---|---|---|---|
|
STEP 01
Site Gate Arrival, Principal Contractor Induction & Pre-Start Inspection (Harbourline Commercial Builders (Sample Specimen))
|
|
L3xC4=12 (HIGH) |
|
L1xC3=3 (LOW)
Role: PCBU / Subcontractor Site Supervisor & All Crew
|
|
STEP 02
Electrical Isolation, Lock-Out Tag-Out (LOTO), Prove De-Energised & Circuit Work (NSW WHS s 291(k))
|
|
L4xC5=20 (EXTREME) |
|
L1xC3=3 (LOW)
Role: Licensed Electrician / SAA Installer
|
|
STEP 03
Working at Heights (> 2 Metres): Edge Protection, Scaffold Access & Brittle Surfaces (NSW WHS s 291(a))
|
|
L4xC5=20 (EXTREME) |
|
L1xC3=3 (LOW)
Role: Site Supervisor & Ticketed Height Crew
|
|
STEP 04
Powered Mobile Plant, Crane Lifting & EWP Movement Separation (NSW WHS s 291(o))
|
|
L4xC5=20 (EXTREME) |
|
L1xC3=3 (LOW)
Role: Plant Operator, Dogman & Site Supervisor
|
|
STEP 05
Crystalline Silica Substance (CSS) Drilling, Chasing & Cutting Controls (NSW WHS Reg 2025 Chapter 8A)
|
|
L3xC4=12 (HIGH) |
|
L1xC2=2 (LOW)
Role: PCBU / Subcontractor Site Supervisor & Tool Operators
|
|
STEP 06
Testing, Commissioning, Housekeeping, Waste Removal & Safe Demobilisation
|
|
L3xC3=9 (HIGH) |
|
L1xC2=2 (LOW)
Role: PCBU / Subcontractor Site Supervisor
|
5. Mandatory Licences, High-Risk Work Classes & Australian Standards
- Unrestricted State Electrical Contractor & Electrician Licence
- General Construction Induction Card (White Card)
- AS/NZS 4836:2023 Safe working on or near low-voltage and extra-low-voltage electrical installations
- AS/NZS 3000:2018 Wiring Rules & AS/NZS 3012:2019 Construction and demolition sites electrical installations
- CPR & Low Voltage Switchboard Rescue Kit currency (refreshed within 12 months)
6. Worker Consultation & Gate Sign-On Sheet
ALL WORKERS MUST READ & SIGN PRIOR TO HRCW STARTBy signing below, each worker confirms they hold a current General Construction Induction Card (White Card) and required trade/HRWL licences, were consulted in reviewing site-specific hazards, and agree to follow the Hierarchy of Controls in this SWMS.
| # | Worker Full Name | Trade / Role | White Card / HRWL Licence No. | Date (DD/MM/YYYY) | Worker Signature |
|---|---|---|---|---|---|
| 01 | Jordan Vance (Sample Leading Hand) | Electrical Supervisor | 26/11/2026 | ||
| 02 | |||||
| 03 | |||||
| 04 | |||||
| 05 | |||||
| 06 |
7. Implementation, On-Site Monitoring, Stop-Work & Review Protocol
WHS Regulation 2025 (NSW) ss 299 to 303 (reg 299(2)(d), reg 299(3)(a)(ii), reg 300 & reg 302)Baseline trade controls prepared for 142 Macquarie Street, Parramatta NSW 2150; nominated supervisor sights and aligns with site-specific rules and emergency procedures in the WHS Regulation 2025 (NSW) s 299(3)(a)(ii) Principal Contractor WHS Management Plan at gate induction prior to work starting.
- Provide this site-specific SWMS to Harbourline Commercial Builders (Sample Specimen) for gate review and acceptance prior to commencing any High-Risk Construction Work.
- Brief all workers at the pre-start toolbox talk in plain language, inspect physical site hazards at the work face, and record each worker’s White Card / HRWL number and signature in Section 6.
- Verify all physical isolation locks, edge protection, shoring, plant pre-starts, and rescue equipment are installed before tools are energised.
- Nominated PCBU / Subcontractor Site Supervisor conducts visual spot-checks at shift start, after breaks, and whenever concurrent trades enter adjacent zones.
- Coordinate daily exclusion zones, crane/plant movements, and permit-to-work handovers with the Principal Contractor Site Supervisor.
- Review and revise this SWMS immediately (WHS Regulation 2025 (NSW) ss 38 & 302) whenever: (a) a control measure does not control the risk as intended; (b) a notifiable incident or near-miss occurs; (c) site conditions, plant, trade scope, or work systems change; or (d) a Health and Safety Representative (HSR) or Principal Contractor requests a review.
8. Emergency Response & Principal Contractor Gate Sign-Off
Emergency Response: In a life-threatening emergency call Triple Zero (000) Emergency Services immediately and notify the Principal Contractor Site Supervisor via site UHF channel or gate office.
Muster Point: Awaiting site confirmation at 142 Macquarie Street, Parramatta NSW 2150: record Principal Contractor Emergency Muster Point ________________________ and Induction Time ____:____ prior to work start.
Trade Rescue Gear: Insulated LV Rescue Kit staged at active switchboard plus spotter holding current CPR & LV Rescue competency.
Medical Centre: Record Principal Contractor nominated hospital / medical centre displayed on site gate noticeboard prior to work start.
Before signing below and commencing High-Risk Construction Work, I confirm I have inspected physical workplace conditions, consulted the workers carrying out the work, verified or adapted the suggested controls in Section 4 to match actual site circumstances, and recorded the site muster point and induction time.
Principal Contractor representative acknowledges receipt and review of this site-specific SWMS prior to High-Risk Construction Work commencing on site.
SiteSWMS.com.au is self-serve commercial document software published in Sydney by Malloy Co Pty Ltd (ABN 61 704 474 055) that prepares editable Safe Work Method Statements aligned to published Australian WHS and Victorian OHS regulations; before High-Risk Construction Work starts, the PCBU/employer and nominated site supervisor inspect physical site conditions, consult workers, and confirm site-specific controls.